| Projected
Non-Building Costs: |
Building Square
Footage: __________ s.f.
Construction Cost per s.f. $_________ |
| Building Cost:
$___________________ |
| |
Cost
Range |
|
| Category/Item |
High |
Medium |
Low |
Your
Cost |
| Professional Fees |
|
|
|
$_____ |
Architect
(% bldg cost) |
16% |
10% |
4% |
$_____ |
Structural Engineer
(% bldg cost) |
2.5% |
2.0% |
1.5% |
$_____ |
| Landscape Architect |
57,500 |
28,750 |
11,500 |
$_____ |
| Surveyor - Topo & Staking |
9,200 |
5,750 |
2,875 |
$_____ |
| Soils Engineer |
6,900 |
4,600 |
2,300 |
$_____ |
| Septic Engineering |
5,750 |
3,750 |
1,725 |
$_____ |
| Interior Designer |
17,250 |
10,350 |
3,450 |
$_____ |
$/sf,
Subtotal |
|
|
|
$_____ |
| |
|
|
|
|
| Government Charges |
|
|
|
|
| Plancheck (per sf of bldg) |
1,260 |
875 |
710 |
$_____ |
| Building Permit (per sf of bldg) |
1,980 |
1,650 |
1,485 |
$_____ |
| Park Fees |
3,263 |
2,720 |
2,447 |
$_____ |
| Septic System Permit |
3,480 |
2,842 |
2,203 |
$_____ |
| Driveway Encroachment |
1,026 |
726 |
426 |
$_____ |
| Well Permit |
762 |
667 |
573 |
$_____ |
| Affordable Housing In-Lieu Fee (per sf of bldg) |
- |
- |
- |
$_____ |
| Traffic Mitigation |
13,180 |
9,673 |
6,166 |
$_____ |
| School Mitigation |
12,492 |
8,838 |
5,184 |
$_____ |
$/sf,
Subtotal |
|
|
|
$_____ |
| |
|
|
|
|
| Utility Fees |
|
|
|
|
| Water Meter or Well Inspection |
300 |
210 |
120 |
$_____ |
| Water Connect Fee |
12,000 |
8,400 |
4,800 |
$_____ |
| Sewer Connect Fee |
10,870 |
6,635 |
2,400 |
$_____ |
| Telephone Connect Fee |
480 |
300 |
120 |
$_____ |
| PG&E Design Fee |
2,400 |
1,800 |
1,200 |
$_____ |
| Elect Service Line (includes trenching; per lf) |
22 |
17 |
12 |
$_____ |
| Gas Line (includes trenching; per lf) |
17 |
13 |
10 |
$_____ |
| Telephone Line (includes trenching; per lf) |
10 |
7 |
5 |
$_____ |
$/sf,
Subtotal |
|
|
|
$_____ |
| |
|
|
|
|
| Sitework |
|
|
|
|
| Septic System |
34,500 |
18,400 |
11,500 |
$_____ |
| Well drilling |
17,250 |
11,500 |
5,750 |
$_____ |
| Water Pump, Tank, & Line |
13,800 |
9,200 |
4,600 |
$_____ |
| Water Treatment System |
11,500 |
7,475 |
3,450 |
$_____ |
| Driveway (per sf of drive) |
3.68 |
2.82 |
1.96 |
$_____ |
| Site Grading (per sf of bldg) |
23 |
9 |
5 |
$_____ |
| Swimming Pool (per sf) |
150 |
127 |
104 |
$_____ |
| Site walls (3' tall average, per lf) |
385 |
230 |
75 |
$_____ |
| Site patios and walks(/sf) |
40 |
21 |
9 |
$_____ |
$/sf,
Subtotal |
|
|
|
$_____ |
| |
|
|
|
|
$/sf,
Total Cost |
|
|
|
$_____
|
|